Assistant General Manager Reports

Assistant General Manager Report – April 2018

by Chris Herring Building and Infrastructure: Bell Center Replacement of the damaged ceiling in the Bell Center indoor spa began on Monday, April 16. Work includes the removal of the existing ceiling, replacement of existing lighting with dimmable LED fixtures, replacement of the ceiling and painting of the ceiling and […]

Read More

Assistant General Manager Report – March 2018

by Chris Herring Building and Infrastructure: Sun Bowl Lighting modifications at the Sun Bowl began March 26, 2018. Lighting will be enhanced with LED floodlights at the rear of the Sun Bowl that will provide additional lighting into and behind the bowl area after shows. Additionally, LED light bollards will […]

Read More

Assistant General Manager Report – February 2018

by Chris Herring Building and Infrastructure: Oakmont Center Fabrication and installation of the cantilever shade structure are awaiting Maricopa County permit approval. Contractor is USA Shade. (Cost – $24,172) Lakeview Center/Lakeview Lanes The renovation of the east restrooms at Lakeview Lanes has been completed and reopened on Saturday, February 17. […]

Read More

Assistant General Manager Report – January 2018

by Chris Herring Building and Infrastructure: Multiple Locations The RCSC WiFi services were originally installed in 2011 with usage growing over time. We are starting the process of upgrading the WiFi services at all RCSC locations (Centers and Snack Shops) which will take approximately 4-6 weeks to complete. These upgrades […]

Read More

Assistant General Manager Report – December 2017

by Chris Herring Building and Infrastructure: Oakmont Center The 16’ x 32’ cantilever shade structure has been delayed due to designed size and building setback requirements. This structure is pending size redesign and variance approval from by Maricopa County Planning and Development and Maricopa County Environmental Services Department. Contractor is […]

Read More

Assistant General Manager Report — November 2017

by Chris Herring Building and Infrastructure: Oakmont Center A 16’ x 40’ cantilever shade structure is being engineered and will be submitted for permit as soon as some important code questions are answered by Maricopa County Planning and Development and Maricopa County Environmental Services Department. Contractor is USA Shade. (Cost […]

Read More

Assistant General Manager Report – October 2017

by Chris Herring Building and Infrastructure: Oakmont Center A 16’ x 40’ cantilever shade structure is being engineered and will be submitted for permit very soon. The permit submission was delayed due to building setback measurement verification. The new shade structure will be installed on the west end of the […]

Read More

Assistant General Manager Report – September 2017

by Chris Herring Building and Infrastructure: Oakmont Center A 16’ x 40’ cantilever shade structure has been submitted for permits. The new shade structure will be installed on the west end of the Oakmont pool deck. Contractor is USA Shade. (Cost – $24,172) Fairway Center Roof leaks found over the […]

Read More

Assistant General Manager Report – August 2017

by Chris Herring Building and Infrastructure: Oakmont Center A 16’ x 40’ cantilever shade structure will be installed this year on the west end of the Oakmont pool deck. Contractor is USA Shade. (Cost – $24,172) Fairway Center Roof leaks were found in the music room and band equipment storage […]

Read More

Assistant General Manager Report – July 2017

by Chris Herring Building and Infrastructure: Multiple Locations Since an aggressive HVAC (Heating, Ventilation & Air Conditioning) replacement plan was implemented in 2006, RCSC has enjoyed many years of reduced energy costs and minimal summer breakdowns to its 324 unit HVAC and Evaporative cooling equipment plant. Unfortunately, 2017 has been […]

Read More