By: Jim Wellman General Centers Information The RCSC is making plans to update the landscaped areas around Bell and Sundial Centers. The work will include raking & cleaning the existing rocked areas, repairing irrigation lines to plants, trees and shrubs and installing additional decorative rock in the planter areas. Contractor […]

Read More

Assistant General Manager Report – December 2011

By: Jim Wellman General Centers Information Cardio equipment instruction manuals have been assembled and placed at all fitness rooms for cardholder reference. A special thank you goes to Frank Furey the RCSC fitness technician for making this happen. In 2011 the RCSC received a total of $11,142 from Arizona Public […]

Read More

Assistant General Manager Report – October 2011

By: Jim Wellman General Centers Information I would like to open my report today with some information about the new pool covers, or pool blankets as some people call them. In early 2011 the RCSC placed an order for insulated pool blankets for the Mt. View, Oakmont, Lakeview, Bell Lap, […]

Read More

Assistant General Manager Report – September 2011

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway Phase 2 project continues to progress towards completion following the RCSC’s receipt of the additional pool/spa permit from Maricopa County Planning and Development. Items yet to be completed have dwindled down to the following: [list1] Installation of […]

Read More

Assistant General Manager Report – August 2011

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway phase II project continues on budget but late in opening due to an additional pool/spa permit required by Maricopa County Planning and Development. The building itself is completed except for a few minor touch-ups. The pools and […]

Read More

Assistant General Manager Report – April 2011

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway, phase II project remains on schedule with work underway as follows: The roof over the cardio, weight room & south track area has been completed, which is allowing the installation of drywall, paint & tile in the […]

Read More

Assistant General Manager Report – February 2011

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway, phase II project remains on schedule with work underway as follows: The masons continue to lay the final remaining block around the center. Iron workers have installed most of the corrugated pan in preparation for ramp concrete. […]

Read More

Assistant General Manager Report – January 2011

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway Phase II project remains on schedule with work under way as follows: The masons are laying block and are at or nearing the top of the walls on the majority of the building. Iron workers have installed […]

Read More

Assistant General Manager Report – December 2010

By: Jim Wellman Fairway Center and South, Quail Run Pro Shops The Fairway Phase 2 project remains on schedule with the recent installation of 95% of the concrete floor plank. CMU block continues to be installed as the walls rise to encompass the second level of the building. Completion of […]

Read More

Assistant General Manager Report – October 2010

By: Jim Wellman Oakmont Center & North Pro Shop To improve filter flow rate and water quality, the Oakmont pool filters were replaced with commercial sized units. Contractor was Jasper Clear Pool. (Cost – $4,352) Fairway Center and South, Quail Run Pro Shops Fairway Phase 2 project remains on schedule […]