by Jim Wellman
Lakeview Center / Lakeview Lanes / Viewpoint Lake / Duffeeland
- Duffeeland Dog Park major renovations are completed and the dog park was reopened to cardholders on August 20, 2015. Contractors were Wadsworth Construction, Double R Masonry, B&C Tree, CCBG Architectural and Sav-on-Fence. (Cost – $136,213)
- Replacement of the deteriorated vinyl siding on the second level at Lakeview Center is now completed. (Cost – $16,700)
- The lake wall repairs around Viewpoint Lake are nearing completion. After a boat trip around the perimeter of the lake on July 21st all the recent repairs to the lake wall look good except one by the 103rd Ave overflow and a new location on the West wall by Lakeview Center. Contractor is Waterworks by George. (Estimated Cost – $10,000)
- Lakeview Center and Lakeview Lanes parking lots were seal-coated and re-striped. Contractor was Swaine Asphalt. (Cost – $22,511)
- The cardholder services and clubs offices are currently undergoing a complete renovation. Renovation work includes complete demolition, new framed interior walls, ceilings, LED lighting, flooring, automatic entry doors and some furniture. Contractor is Ken McIntyre Construction, Accel Electric, CCBG Architectural, D.H. Pace and Resource Flooring. (Cost – $171,206)
- Remodel work is currently underway at Lakeview lanes. The work includes removal of all the old ball racks and counters, replacement of flooring in the bowler’s area and installation of new counter tables with “house” ball racks. Contractors include DFG Builders, Resource Flooring and the RCSC Skilled Trades Team. (Cost – $55,248)
Sundial Center
- Except for the walls surrounding the equipment building, the new Verizon cell tower and equipment building are installed and functioning. The Verizon contractor was contacted August 9th and he informed me that a mold for the current style block used at Sundial had to be made before the block could be casted. This process has delayed the block wall construction, but he assures me that he will make the installation of the block a priority and expects to begin construction soon.
- The two assisted shower rooms at Sundial have been remodeled and were reopened to cardholders on August 28, 2015. Contractor was Robert Porter Construction. (Cost – $49,074)
- The two new unisex ADA restrooms in the lobby area of Sundial auditorium are progressing very well. The restrooms are complete except for the installation of sinks, toilets and some punch list items. If all goes well, the two new ADA restrooms will be opened for cardholder use in approximately two weeks. Contractor is DFG Builders. (Cost – $49,848)
- The Sundial pools and spas will be closed beginning September 7, 2015 so new LED overhead lighting can be installed. This shutdown is expected to last approximately 14-18 days. Contractor is Harmon Electric. (Cost – $52,500)
- Sundial Center parking lots were seal-coated and restriped. Contractor was Swaine Asphalt. (Cost – $20,864)
Bell Center / Bell Lanes
- Bell Center parking lots were seal coated and restriped. Contractor was Swaine Asphalt. (Cost – $44,519)
- Remodel work is currently underway at Bell lanes. The work includes removal of all the old ball racks and counters, replacement of flooring in the bowler’s area and installation of new counter tables with “house” ball racks. Contractors include DFG Builders, Resource Flooring and the RCSC Skilled Trades Team. (Cost – $47,812)
Fairway Center
- Shutdown of the fitness room, pools and walking track occurred on August 24, 2015 and is expected to last until August 31, 2015. The closure allows staff and contractors to complete needed repairs, perform maintenance work and thoroughly clean this portion of the facility.
- Contractor bid proposals have been received and bid commission approval obtained for the construction of a shade canopy and installation of artificial grass at the Best Friends Dog Club training facility. Unfortunately, the structural engineering for the shade canopy was not correct and had to be resubmitted for corrections. As soon as the engineering is completed again, the architect will submit this project to Maricopa County Planning and Development Department for the building permit. Contractors include Arizona Bag and Shade, Sun Burst Landscaping, and CCBG Architectural. (Cost – $80,909)
Mt.View Center
- Ninety-six thermal solar panels at Mt. View Center are scheduled for replacement. The project also includes the replacement of some 4” piping and upgrades to the electronic controller. Contractor is General Solar. (Cost – $37,614)
Riverview Pro Shop Building
- The Riverview pro shop, patio and building renovation project is nearing completion with only a few things left to do, such as installation of a new service counter in the pro shop, epoxy coating of the patio slabs, reinstallation of offices, installation of interior and exterior furniture, display cases, parking lot seal-coating and re-striping, deep cleaning of the entire facility and passing the final building inspections. Contractors include Ken McIntyre Construction, Accel Electric, Regional Paving and CCBG Architectural. (Cost – $524,236)
Skilled Trades Department
- The RCSC Skilled Trades department completed 174 work orders during the last two weeks of July 2015 and the first two weeks of August 2015.
Centers Operations Report
- We recently hired Michael Janicki to fill the South Area P.M. Supervisor position. He will supervise Lakeview, Oakmont, Fairway and Mountain View Recreation Centers. He will also oversee the utility staff at North, Quail Run and South golf course pro and snack shops.
- New patio furniture has arrived at the Bell Tennis Center. There are now 12 tables and 48 chairs under the big awning, available for relaxing and socializing between tennis matches.
- Additional lighting has been installed for the disco ball in the Bell Social Halls. This will greatly enhance the ambiance when it is turned on during special events and dances.