by Jim Wellman General Centers Projects and Information The card access equipment and software for the Fairway card access system is installed and tested. RCSC employees have received software training. Distribution of access devices to dedicated clubs and migration from keys to the new system will occur the week of […]
Assistant General Manager Reports
Assistant General Manager Report – March 2014
by Jim Wellman General Centers Projects and Information The card access equipment for the Fairway installation has arrived. Meetings are being scheduled with dedicated clubs at Fairway to discuss the new systems and their room access needs and concerns. Once these discussions are completed and the software installed on the […]
Assistant General Manager Report – February 2014
By Jim Wellman General Centers Projects and Information Card Access equipment is currently on order for all club room doors and the East entrance door for Fairway Center. Once the equipment arrives I will schedule meetings with the dedicated clubs at Fairway to discuss the new systems and their room […]
Assistant General Manager Report – January 2014
by Jim Wellman General Centers Projects and Information • Robert Ortiz was hired in January 2014 to assume the position of Grounds Supervisor. Robert will oversee the landscaping maintenance at all RCSC centers and the maintenance of all Lawn Bowling greens. Robert’s extensive training and experience in turf management will […]
Assistant General Manager Report – December 2013
by Jim Wellman General Centers Projects and Information Vern White has filled the Building and Infrastructure Coordinator vacancy created when Josephine Karacsony resigned her position. Mr. White comes with some impressive skills and experience which also include working the last two years at Bell Center as Utility Worker and Lead […]
Assistant General Manager Report – November 2013
by Jim Wellman General Centers Projects and Information The Quail Run Maintenance asphalt project will not be completed in 2013 due to operational and planning issues. Regional Paving has already been awarded the contract for this project and will complete it once the RCSC determines the commencement date. Mt. View Center […]
Assistant General Manager Report – October 2013
by Jim Wellman General Centers Projects and Information Unfortunately during the month of October 2013 Josephine Karacsony, Building and Infrastructure Coordinator, left the RCSC. Josephine will surely be missed as she was instrumental in the completion of many projects and other special assignments. The B&I department wishes Josephine huge success in […]
Assistant General Manager Report – September 2013
by Jim Wellman General Centers Projects / Information The installation of all RCSC Photo Voltaic (PV-Electricity producing) solar systems and their respective monitoring applications are completed. Several cardholders have expressed their appreciation for the added benefit of shade provided by the solar canopies during the summer. Ceiling fans were replaced by […]
Assistant General Manager Report – August 2013
by Jim Wellman General Centers Projects / Information • All Photo Voltaic (PV-Electricity producing) systems are now completed and only the connection of the monitoring system remains on a few systems. Cardholders continue to express their appreciation for the solar canopies which provide shaded parking during this hot summer. Mt. […]
Assistant General Manager Report – July 2013
by Jim Wellman General Centers Projects / Information Installation of the Photo Voltaic (PV-Electricity producing) systems is winding down with the last solar equipment connections made at Lakeview Center the weekend of July 18, 2013. The following systems are online and producing electrical power at the time of this report: […]